Energy Hub
Energy Hub for Data Center
The Sturovo Industrial Park is building a comprehensive energy ecosystem with 100 MW+ capacity designed to power a data center running on renewable sources. The combination of our own photovoltaic power plant, battery storage systems, and planned expansion creates a unique energy platform in Central Europe.
Solar Energy
Existing: 24 MW Photovoltaic Power Plant
Planning: expansion by 6 MW (2028)
Power Supply
Voltage Level: 110 kV / 22 kV / 6.3 kV
Existing: Electricity Production 50 MW
Planning: 100 MW+ (2030)
Battery Energy Storage (BESS)
Existing: 12.4 MW (6.4 MW + 6 MW)
Planning: expansion by 10 MW (2028)
Gas Turbine Power Plant
Capacity: 70 MW (2 × 35 MW)
Timeline: 2028 – 2030